Order Description:
Commissioning Instrumentation & Controls (SPPA-T3000)

Client:
Siemens

Volume:
100,000 Euro

Period:
2011

Scope of Work:
›  prepare commissioning schedule and test plan
›  prepare and maintain all site operation documentation and check lists
›  supervise preparation, installation and maintenance of commissioning equipment
›  supervise integrated test during cold and hot commissioning
›  manage change requests
›  release requested modifications
›  perform claim management
›  supervise quality documentation
›  release and organize reliability run and performance test