Open Cycle Power Plant AGPS (875 MW) Erbil – Kurdistan Region, Iraq

Open Cycle Power Plant AGPS (875 MW)

Erbil – Kurdistan Region, Iraq

Order Description:
Supervision / Commissioning

Client:
ABB

Volume:
720,000 Euro

Period:
2011

Scope of Work:
Supervision Gas Turbine:
›  Erection of Gas Turbine & Generator Type GE Frame 9E incl. components
›  Alignment of Gas Turbine & Generator incl. components
›  Stainless steel sleeve & insulation (cladding)
›  Steel structures
›  Piping
›  Equipment (cranking motor, cooling fans, CO2 container etc.)
Supervision Piping:
›  On Base Lube Oil Piping
›  On Base C&SA piping
›  On Base Fuel piping
›  On Base Atomising Air
›  On Base Fire Fighting Piping
›  On Base Air Instrumentation
›  On Base Fuel Distribution
›  Off Base Cooling Water Piping
›  Off Base Oil Waste Piping
›  Off Base Fire Protection
›  Off Base Wash Water piping (pre fab)
›  Off Base Compressed Air (pre fab)
›  Off Base Fuel Oil System (pre fab)
Commissioning Electrical System:
›  protection relay testing by primary and/or secondary current/voltage injection for feeders,couplers, outgoing feeders, motorfeeders, transformers, softstarters,
frequency converters etc. in MV and LV switchgears
›  Interlock testing at HV, MV and LVswitchgears
(electrical and mechanical) for feeders, couplers outgoing feeders, etc.
›  HV-testing for switchgears, breakers, busbars and cables
›  VT and CT testing by primary and/or secondary injection for protection relays,
measurement equipment, synchronizing
equipment.