Pump Station Shoaiba
Jeddah – Saudi Arabia
Order Description:
Commissioning of Electrical System
Client:
ABB AG
Volume:
580,000 EUR
Period:
2008 - 2010
Scope of Work:
Autonomous and independent supervision incl. protocols of the following components:
Main pump station Shoiba:
Booster pump station:
Commissioning of Electrical System
Client:
ABB AG
Volume:
580,000 EUR
Period:
2008 - 2010
Scope of Work:
Autonomous and independent supervision incl. protocols of the following components:
Main pump station Shoiba:
| › | 28 pcs. LV-switchgears 13.8 KV |
| › | 3 pcs. HV-transformers 63 MVA 380/13.8 KV |
| › | 3 pcs. LV-transformers 1000 KVA |
| › | 3 pcs. transformer protection systems |
| › | 8 pcs. HV-motors |
| › | 3 pcs. Motor Starters |
| › | 5 pcs. LV-switchgears 0.4 KV |
| › | 11 pcs. LV-sub distributions |
| › | 1 pcs. UPS-system |
| › | 1 pcs. Batteries |
Booster pump station:
| › | 20 pcs. MV-switchgears 13.8 KV |
| › | 32 pcs. LV-transformers 630 KVA |
| › | 8 pcs. HV-motors |
| › | 3 pcs. LV-switchgears 0.4 KV |
| › | 7 pcs. LV-sub distributions |
| › | 1 pcs. UPS-system |
| › | 1 pcs. Batteries |