Gas Fired Power Plant Suleymaniyah (750 MW) Erbil – Kurdistan Region, Iraq

Gas Fired Power Plant Suleymaniyah (750 MW)

Erbil – Kurdistan Region, Iraq

Order Description:
Supervision / Commissioning

Client:
ABB

Volume:
820,000 EUR

Period:
2010 – 2011

Scope of Work:

Supervision Gas Turbine:
Erection of Gas Turbine & Generator Type GE Frame 9E incl. components
Alignment of Gas Turbine & Generator incl. components
Stainless steel sleeve & insulation (cladding)
Steel structures
Piping
Equipment (cranking motor, cooling fans, CO2 container etc.)

Supervision Piping:
On Base Lube Oil Piping
  On Base C&SA piping
On Base Fuel piping

On Base Atomising Air

On Base Fire Fighting Piping

On Base Air Instrumentation
On Base Fuel Distribution
Off Base Cooling Water Piping
Off Base Oil Waste Piping
Off Base Fire Protection
Off Base Wash Water piping (pre fab)
Off Base Compressed Air (pre fab)
Off Base Fuel Oil System (pre fab)

Overall Commissioning:
prepare commissioning schedule and test plan
prepare and maintain all site operation documentation and check lists
supervise preparation, installation and maintenance of commissioning equipment
supervise integrated test during cold and hot commissioning
manage change requests
release requested modifications
perform claim management
supervise quality documentation
release and organize reliability run and performance test
perform training on the job for customer personal

Commissioning Electrical System:
protection relay testing by primary and/ or secondary current/voltage injection for feeders,couplers, outgoing feeders, motorfeeders, transformers, softstarters, frequency converters etc. in MV and LV switchgears
Interlock testing at HV, MV and LVswitchgears (electrical and mechanical) for feeders, couplers outgoing feeders, etc.
HV-testing for switchgears, breakers, busbars and cables
VT and CT testing by primary and/or secondary injection for protection relays, measurement equipment, synchronizing equipment.